Short answer
1,000 standard UK bricks in a half-brick wall need about 0.3 m³ of wet mortar: roughly five 25 kg bags of cement and half a tonne of building sand at a 1 : 4 mix, including 10% for waste. A solid wall one brick thick uses about 30% more mortar per brick, because of the vertical joint down its middle. In the US, 1,000 modular bricks in a single wythe take about 8 cu ft of mortar before waste.
Know the wall size but not the brick count? Use the calculator below by wall area, or start with the brick calculator, which counts bricks and mortar together.
Calculate mortar, cement and sand
Estimates only, for solid bricks laid with full joints. Frogged bricks laid frog-up and perforated bricks take noticeably more. Lime and ready-mixed mortars follow the maker's yields, not these figures.
Mortar per 1,000 bricks and per square metre
Figures from this page's calculator, no waste, 1 : 4 mix:
| Brick and wall | Bricks per m² | Wet mortar per m² | Wet mortar per 1,000 bricks | Cement per 1,000 | Sand per 1,000 |
|---|---|---|---|---|---|
| UK, half brick | 59.3 | 17.6 litres | 0.30 m³ | 111 kg | 495 kg |
| UK, one brick thick | 118.5 | 45.2 litres | 0.38 m³ | 143 kg | 635 kg |
| US modular, one wythe | 6.9 per sq ft | 0.055 cu ft per sq ft | 8.0 cu ft | 188 lb | 836 lb |
| US modular, two wythes | 13.7 per sq ft | 0.141 cu ft per sq ft | 10.3 cu ft | 241 lb | 1,072 lb |
| German NF, half brick | 49.4 | 18.2 litres | 0.37 m³ | 138 kg | 614 kg |
| Australian, single leaf | 48.4 | 16.8 litres | 0.35 m³ | 130 kg | 578 kg |
Bigger bricks use more mortar per brick but fewer bricks per square metre, so mortar per square metre of a single-leaf wall stays close to 17 to 18 litres whatever the brick.
How much mortar for 100 bricks?
100 standard UK bricks in a half-brick wall need about 30 litres of wet mortar: roughly 11 kg of cement and 50 kg of building sand at a 1 : 4 mix, or about 33 litres, 12 kg of cement and 55 kg of sand with 10% for waste. That is half a 25 kg bag of cement and two 25 kg bags of sand, a typical small garden job. In the US, 100 modular bricks in one wythe take about 0.8 cu ft of mortar before waste.
| Per 100 bricks, 1 : 4 mix | Wet mortar | Cement | Building sand |
|---|---|---|---|
| UK, half brick, no waste | 30 litres | 11 kg | 50 kg |
| UK, half brick, +10% waste | 33 litres | 12 kg | 55 kg |
| UK, one brick thick, +10% waste | 42 litres | 16 kg | 70 kg |
| US modular, one wythe, +10% waste | 0.88 cu ft | 21 lb | 92 lb |
Using bags of ready-mixed mortar? Divide the wet yield printed on the bag by the mortar each brick takes: about 0.3 litres per UK brick in a half-brick wall (0.38 litres one brick thick), or about 0.008 cu ft per US modular brick in one wythe. For example, a bag that yields 12 litres of mortar would lay roughly 40 UK bricks before waste. If the bag's own coverage figure is lower, plan on that, since makers allow for frogs, thicker joints and waste. Same figures as the per-1,000 table above, divided by ten.
Which mortar mix should I use?
Mortar should be a little weaker than the bricks it joins, so any cracking follows the joints, which are easy to repoint, rather than the bricks. Common rules of thumb:
- 1 : 3 cement : sand for copings, work below the damp-proof course, retaining walls and dense engineering bricks.
- 1 : 4 with a plasticiser for most general outdoor walls in ordinary facing bricks.
- 1 : 5 or 1 : 6 with a plasticiser for softer bricks and sheltered or internal walls.
- Lime mortar for old, soft brickwork; hard cement mortar can trap moisture and spall old bricks (see repointing tips).
- US mortar types: Type N for most above-grade walls, Type S for below-grade, retaining and high-wind work, Type M for heavy loads below grade.
Follow a structural engineer's or the brick maker's specification where there is one.
How the calculation works
Each brick, with its share of joints, occupies (brick length + joint) × (brick height + joint) of wall face. Mortar is the wall's volume minus the bricks' volume. A wall one brick thick also has a vertical collar joint between its two leaves. Wet mortar is converted to dry materials using the common estimating rule that dry ingredients shrink by about 30% when mixed, with loose bulk densities of about 1,440 kg/m³ for cement and 1,600 kg/m³ for damp building sand. These are the same formulas as the brick calculator.
Last updated: 30 October 2026. Every figure on this page comes from the calculation described above; no results are guaranteed, and actual quantities depend on your bricks, joints, site and workmanship. This page is general information and an estimating aid, not professional, structural or engineering advice. Footing sizes, wall heights and mortar or concrete mixes depend on soil, exposure and local building rules, so confirm them with your local building control office or a qualified professional before you build.
Mortar FAQ
How much mortar do I need per 1,000 bricks?
For standard UK bricks (215 × 102.5 × 65 mm) with a 10 mm joint, about 0.30 m³ of wet mortar per 1,000 bricks in a half-brick (single-leaf) wall, or about 0.38 m³ in a solid wall one brick thick, before waste. US modular brick with a ⅜ in joint takes about 8 cu ft per 1,000 in a single wythe. Frogged bricks laid frog-up take more.
How many bags of cement do I need for 1,000 bricks?
About 111 kg of cement for 1,000 UK bricks in a half-brick wall at a 1:4 cement-to-sand mix, which is five 25 kg bags once you add 10% for waste (about 122 kg). A one-brick-thick wall needs about 143 kg before waste, so six bags.
How much sand do I need for 1,000 bricks?
About 0.5 tonnes (495 kg) of building sand for 1,000 UK bricks in a half-brick wall at a 1:4 mix, or about 545 kg with 10% waste. A one-brick-thick wall needs about 635 kg before waste.
How much mortar do I need for 100 bricks?
About 30 litres of wet mortar for 100 UK bricks in a half-brick wall, which is roughly 11 kg of cement and 50 kg of building sand at a 1:4 mix, or about 12 kg and 55 kg with 10% for waste. 100 US modular bricks in a single wythe take about 0.8 cu ft of mortar.
How much mortar do I need per square metre of brickwork?
About 18 litres (0.018 m³) of wet mortar per m² for a UK half-brick wall with 10 mm joints, and about 45 litres per m² for a solid wall one brick thick, because the thick wall also has a vertical collar joint down the middle.
What mortar mix should I use for brickwork?
For general outdoor brickwork 1 part cement to 4 parts building sand (with plasticiser) is the common choice. Use a stronger 1:3 mix for copings, work below the damp-proof course and engineering bricks, and a weaker 1:5 or 1:6 for soft bricks and sheltered or internal walls. Mortar should be weaker than the brick, and old soft brickwork usually needs a lime mortar. In the US, Type N is the usual mortar for above-grade walls and Type S for below-grade and retaining walls.